State Grid Xiamen Power Supply Company: "EASIER" service is iteratively upgraded, and "Xiamen speed" is refreshed again.
The waves are surging and the sails are strong. Xiamen is a "hot land" for investment and entrepreneurship, and also a "fertile ground" for the growth of entrepreneurs.
On March 1, this year, the first comprehensive and basic regulation of Xiamen’s business environment construction, the Regulations of Xiamen Special Economic Zone on Optimizing Business Environment, was officially implemented. State Grid Xiamen Power Supply Company implements the relevant provisions of the Regulations with the highest standards, builds a sub-brand of "EASIER Power Supply" that is "economical, open, fast, collaborative, efficient and reliable", and iteratively upgrades a series of new service measures, effectively making customers feel that "there are fewer power supply links, shorter power supply time, lower power supply cost and more convenient power supply", which adds vigorous impetus to Xiamen’s economic development.
"Access to electricity" is an important yardstick to measure the level of a city’s business environment. Xiamen’s "access to electricity" index was rated as "national benchmark" and ranked first in the province for four consecutive years (2018-2021). Behind the report card is the province’s first "open door to receive electricity" model, "pilot electricity" and "overall lease of electricity projects"; The "zero investment" policy for external projects of 1,250kVA and below is the first in China; Establishing the first carbon ecological map in China … Every innovation is a vivid footnote for Xiamen Power Supply Company in optimizing the business environment.
"One Step Forward" Construction of Electric Power and "Speed Up by Raising Files"

State Grid Xiamen Power Supply Company fully serves the power supply guarantee of "Xiamen Times" project (photo by Ye Chengcai)
Power consumption is the first step in project construction.
Apply for the addition of 4 1000 KVA box transformers-In November last year, Tongan Power Supply Service Center of Xiamen Power Supply Company received this "Big Mac" class application for construction electricity. The application is the Xiamen Xinneng ‘an Lithium-ion Battery Production Base Project (Phase I) located in Tongxianggao New City, which is the first tens of billions-level project of energy giant Contemporary Amperex Technology Co., Limited in Xiamen.
Because the enterprise has just settled in Xiamen, and the procedures and materials are still incomplete, Xiamen Power Supply Company has implemented the pilot power supply, putting the process ahead and shortening the time. On November 20th, last year, four temporary power transformers of the project were successfully delivered, setting a record of only 15 days from the application for power consumption to the construction of power consumption.
Formal electricity consumption is a lasting and stable energy guarantee for the project to put into production and reach production. Because the construction process of the 220 kV special substation project of this project can’t meet the urgent requirements of its production line, Xiamen Power Supply Company customized the temporary transition power supply scheme of 10 kV power supply, which was officially electrified on October 30, providing a strong guarantee for the project to be put into production at the end of the sprint.
Ji Chaoqun, head of the engineering department of the headquarters of Tongxiang High-tech New City in Xiamen, said: "Xiamen Power Supply Company intervened in advance in the early stage of design and planning, and the construction continuously refreshed the’ grid speed’, vigorously boosting the development of the 10 billion-level project and the 100 billion industrial chain of Tongxiang High-tech New City."
The data shows that Xiamen Power Supply Company has innovated and integrated the "electricity+investment" model, and has implemented more than 1,200 "pilot" projects.
In August this year, Xiamen Power Supply Company initiated the "open-door power connection" mode in the whole province, and took the lead in building the "open-door power connection" demonstration zone in the third phase of Jimei Software Park, so as to assess the power demand in the zone in advance, simultaneously carry out the construction of supporting power grids, realize the enterprise’s "sending electricity to the door and carrying bags to settle in", and promote the transformation from "enterprise waiting for electricity" to "enterprise waiting for electricity", which is expected to save about 30 million yuan for the enterprises in the demonstration zone.
The policy of benefiting enterprises is "addition" and the cost of electricity is "subtraction"
Xiamen Power Supply Company carved the "dare to try" special zone gene into the bone marrow.
"The project construction budget is about 600,000 yuan, but in the end it only cost less than 250,000 yuan." On March 7 this year, the new transformer of Xiamen Hualv Agricultural Development Co., Ltd. was officially put into use, said Mr. Zhuang, the person in charge of the company.
What makes it affordable is the "zero investment" policy for the construction of external projects of small and medium-sized enterprises with an application capacity of 1,250 KVA or less, which is the first in Xiamen. In the past two years, the policy has saved more than 18 million yuan in construction costs for small and medium-sized enterprises.
Xiamen Power Supply Company set up the Power Business Environment Research Center, which promoted 11 batches of 43 initiatives to be included in the municipal task list, and the government and enterprises cooperated to promote a number of innovative initiatives.
This year, the relevant departments of Xiamen Municipal Government continued to strengthen the policy of benefiting enterprises, and made it clear that the external projects of power customers with a full capacity of 10 kV and above in the whole city will be funded by the government, realizing "zero investment" in the construction of external power facilities for customers, which is expected to save enterprises 360 million yuan a year.
Xiamen Power Supply Company also initiated the "whole electricity leasing" in the whole province, saving users 40% time and 30% expenses on average. Xiamen Xiang ‘an Airport has a tight construction period and many locations, and the operation and maintenance of more than 20 construction box transformers and the disposal of assets after completion have become a problem. Gao Chenjie, the person in charge of the project, said, "The whole electricity leasing service covers the whole process from power supply scheme handling to completion acceptance and power transmission. At present, the acceptance and power transmission of nine construction box transformers have been completed, saving money, time and effort."
Use energy "at a glance" to serve "one stop in place"

Water and electricity network "one-stop" joint operation, bringing more convenience to customers (photo by Lin Xuejun)
There is no end to innovation and service.
As an innovative practice to serve peak carbon dioxide emissions’s goal of carbon neutrality, in November, Xiamen issued the Notice on Matters Related to Xiamen Power System Enterprises’ Application for Technology Innovation Fund, which included the R&D investment of low-carbon energy transformation projects and new power system construction enterprises in Xiamen into the support scope of Xiamen Technology Innovation Fund.
Xiamen Power Supply Company tried first, established the first domestic electric carbon ecological map, opened up the "electricity-carbon-energy" data chain, and made an accurate portrait of the carbon emissions and energy-saving efficiency of the whole society’s electricity customers. At present, it has covered more than 1.6 million all-purpose electricity customers in Xiamen, and achieved monthly dynamic updates to efficiently serve the transformation of energy consumption in the whole society.
Xiamen Taiping Container Manufacturing Co., Ltd. has tasted the sweetness from the electric carbon ecological map and has been successfully selected as a "national green factory". Xiamen Power Supply Company made use of electric carbon ecological map to tailor its energy consumption improvement plan. According to the plan, the enterprise started to implement the 3.91 MW photovoltaic project, which is expected to generate 4.69 million kWh of electricity annually, and reduce carbon dioxide emissions by about 4,678 tons annually, reducing the production and operation costs of enterprises and improving the export competitiveness of products.
In order to promote the reform of "running at most once" to extend to the field of public services, in March this year, the first batch of "water and electricity network" joint window in Xiamen was officially put into operation. At present, there are 32 water and electricity network business outlets and 7 urban administrative service centers in Xiamen, which have realized "one form application, one window comprehensive management", and "I Xiamen" and "online national network" have also realized "one network management". At the same time, the "online state grid" power service will be integrated into the "e-government" terminal in Xiamen, and citizens can handle power service through more than 400 "e-government" self-service terminals in the city. (Liu Yan Zhuang Yingfang Xia Yingxiao)